  1. How many electric vehicle chargers have been installed in your council area, including on streets, motorways and car parks? If you could provide a breakdown over the past 5 years (preferably calendar year).
  2. How many broken chargers have had to be fixed over the last 5 years and what has been the cost of this? If you could provide a breakdown over the past 5 years (preferably calendar year).
  3. How many electric vehicle chargers do you plan to install in 2024? 
  4. How many electric vehicle chargers do you plan to install in 2025? (If applicable)

Response

  1. 2017-18 - 4, 2019 - 4, 2020-21 - 1, 2021-22 23, 2022-23 - 2
  2. Chargers are the property of a 3rd party and all maintenance and repairs including all costs will sit with them.
  3. Approx. 4-7 planned for 2024
  4. None currently planned for 2025