Response A1345369

Response to request for information

Reference

A1345369

Response date

26 July 2021

Request

  1. How many employees are at your organisation?
  2. How many mobile phone and mobile broadband (data only) connections do you currently have?
  3. What is the split between mobile phone and mobile broadband connections?
  4. Who is your mobile phone network provider?
  5. Did you switch providers on your last renewal?
  6. Please provide a monthly breakdown of your total mobile phone contract costs for the past 12 months, and state whether VAT has been included in the numbers given.
  7. Does your contract include a hardware, tech or transformation fund?
  8. If the answer to question 7 is yes, what was the value of the fund upon the signing of the current contract?
  9. How have you sourced the contract?
  10. What is the contract term length?
  11. How long do you have remaining on your current contract?
  12. Who is the primary contact for this contract?

Response

  1. How many employees are at your organisation?
    • Approx. 260
  2. How many mobile phone and mobile broadband (data only) connections do you currently have?
    • Approx. 140
  3. What is the split between mobile phone and mobile broadband connections?
    • Approx. 6
  4. Who is your mobile phone network provider?
    • Telefonica (O2)
  5. Did you switch providers on your last renewal?
    • No
  6. Please provide a monthly breakdown of your total mobile phone contract costs for the past 12 months, and state whether VAT has been included in the numbers given.
    • July 2020 - £2,149.46
    • August 2020 - £1,814.64
    • September 2020 - £2,463.68
    • October 2020 - £1,465.90
    • November 2020 - £2,171.40
    • December 2020 - £1,332.24
    • January 2021 - £1,205.40
    • February 2021 - £1,299.73
    • March 2021 - £1,186.46
    • April 2021 - £1,101.07
    • May 2021 - £1,109.26
    • June 2021 - £1,105.71
    • July 2021 - £1,105.71
  7. Does your contract include a hardware, tech or transformation fund?
    • Yes
  8. If the answer to question 7 is yes, what was the value of the fund upon the signing of the current contract?
    • £12,500
  9. How have you sourced the contract?
    • Direct Award CCS Framework RM3808 LOT 6
  10. What is the contract term length?
    • 2 years
  11. How long do you have remaining on your current contract?
    • 14 months
  12. Who is the primary contact for this contract?
    • Greg Dwyer, ICT Services Chief Information Officer