Response 877768

Response to request for information

Reference

877768

Response date

30 May 2022

Request

Householder applications received between 27 March 2020 to 26 March 2021:

  • The number of householder full planning applications received by yourselves
  • The number of householder full planning applications you received where a decision was made within the 8 week decision making timeframe
  • The number of householder full planning applications that you received where you did not make a decision within the 8 week decision making timeframe
  • The number of written requests for extensions of the period of time within which you have to decide a householder full planning application that you made to the applicants where a decision was not made within 8 weeks

Householder applications received between 27 March 2021 to 09 May 2022:

  • The number of householder full planning applications received by yourselves
  • The number of householder full planning applications you received where a decision was made within the 8 week decision making timeframe
  • The number of householder full planning applications that you received where you did not make a decision within the 8 week decision making timeframe
  • The number of written requests for extensions of the period of time within which you have to decide a householder full planning application that you made to the applicants where a decision was not made within 8 weeks

Response

Householder applications received between 27 March 2020 to 26 March 2021:

- The number of householder full planning applications received by yourselves 944

- The number of householder full planning applications you received where a decision was made within the 8 week decision making timeframe 614

- The number of householder full planning applications that you received where you did not make a decision within the 8 week decision making timeframe 330*

- The number of written requests for extensions of the period of time within which you have to decide a householder full planning application that you made to the applicants where a decision was not made within 8 weeks 153**

Householder applications received between 27 March 2021 to 09 May 2022:

- The number of householder full planning applications received by yourselves 1100

- The number of householder full planning applications you received where a decision was made within the 8 week decision making timeframe 477

- The number of householder full planning applications that you received where you did not make a decision within the 8 week decision making timeframe 623*

- The number of written requests for extensions of the period of time within which you have to decide a householder full planning application that you made to the applicants where a decision was not made within 8 weeks 221**

 

*Note that these figures include applications which were received within the stated time period but either:

(a) have not yet been validated

(b) have been returned as invalid

(c) were withdrawn before a decision

(c) have not yet been decided

 

**Note this figure is actually the number of applications where an extension of time has been requested, rather than the number of extensions of time requested (i.e. does not capture multiple extension of time requests for a single application).