Response 2528714
Response to request for information
Reference
2528714
Response date
15 November 2023
Request
- How many minor planning applications were received by the authority in
- 2020-21,
- 2021-22,
- 2022-23?
- How many minor planning applications were determined by the authority in (
- 2020-21,
- 2021-22,
- 2022-23?
- How many major planning applications were received by the authority in
- 2020-21,
- 2021-22,
- 2022-23?
- How many major planning applications were determined by the authority in
- 2020-21,
- 2021-22,
- 2022-23?
- For major applications determined during 2020-21, how many were determined: (a)
- In under 13 weeks,
- In 13 to 26 weeks,
- In 27 to 52 weeks and
- In more than 52 weeks.
- For major applications determined during 2021-22, how many were determined:
- In under 13 weeks,
- In 13 to 26 weeks,
- In 27 to 52 weeks and
- In more than 52 weeks.
- For major applications determined during 2022-23, how many were determined:
- In under 13 weeks,
- In 13 to 26 weeks,
- In 27 to 52 weeks and
- In more than 52 weeks.
Response
- How many minor planning applications were received by the authority in
- 2020-21 - 361
- 2021-22 - 358
- 2022-23 - 290
- How many minor planning applications were determined by the authority in
- 2020-21 - 306
- 2021-22 - 272
- 2022-23 - 286
- How many major planning applications were received by the authority in
- 2020-21 - 48
- 2021-22 - 52
- 2022-23 - 53
- How many major planning applications were determined by the authority in
- 2020-21 - 44
- 2021-22 - 44
- 2022-23 - 48
- For major applications determined during 2020-21, how many were determined:
- In under 13 weeks - 14
- In 13 to 26 weeks - 15
- In 27 to 52 weeks - 11
- In more than 52 weeks - 4
- For major applications determined during 2021-22, how many were determined:
- In under 13 weeks - 10
- In 13 to 26 weeks - 13
- In 27 to 52 weeks - 12
- In more than 52 weeks - 9
- For major applications determined during 2022-23, how many were determined:
- In under 13 weeks -10
- In 13 to 26 weeks - 12
- In 27 to 52 weeks - 14
- In more than 52 weeks - 12
FOI Responses Planning - 2023
- Response 1000384
- Response 1007826
- Response 1022353
- Response 1039015
- Response 1030348
- Response 1072902
- Response 1078965
- Response 1102599
- Response 1111507
- Response 1803342
- Response 1813582
- Response 1800771
- Response 1135678
- Response 1815704
- Response 1847127