For the period November 2024 which was invoiced by the supplier to you in December, we please require disclosure:

  • For your half-hourly meter portfolio, the grid Electricity kwh’s consumed & the £-value spent excl-vat?
  • The natural Gas kwh’s consumed & the £-value spent excl-vat?
  • Please do also indicate if the electricity is classed as being Green or Brown?

Response

For the period November 2024 which was invoiced by the supplier to you in December, we please require disclosure:

  • For your half-hourly meter portfolio, the grid Electricity kwh’s consumed & the £-value spent excl-vat?
    • 2946.9 KWH/£883.16

  • The natural Gas kwh’s consumed & the £-value spent excl-vat?
    • 60822.6 KWH/£2994.81

  • Please do also indicate if the electricity is classed as being Green or Brown?
    • Green